Legal Drafting – Dispute Resolution (Addison Builders)
Task email
From: Partner
Sent: 4 December 2025
To: Candidate
Subject: Addison Builders Limited
You will recall that we have been waiting for a response to the Letter Before Claim that we sent to Maria and Ian Humphries on behalf of Addison Builders Limited. The couple have instructed solicitors, Faulkners and Co. We have now received a letter in response, denying that any further payment is due to our client on the basis that there were significant defects in the work carried out by Addison Builders Limited. (The letter of response is not supplied for the purposes of this assessment.) The allegation that there were significant defects is denied by our client.
I attach a draft initial statement from John Evans, the managing director of Addison Builders Limited, which should provide you with all the information you need. You will notice the draft initial statement at paragraph 4 refers to a written agreement. We do not have a copy of this at present but John Evans has assured me that he will provide it for us and that its terms are as stated in his witness statement so you should proceed on that basis.
We are instructed to commence proceedings. I intend to send the Claim Form to the court for issue with the Particulars of Claim on 8 December 2025. Please draft the Particulars of Claim using the template provided. Some fields have been pre-populated by our case management system.
The written agreement has no provision for interest so please include a claim for statutory interest pursuant to County Courts Act 1984, s.69 at the rate of 8% per year, the figures for which are:
157 days to 8 December at 8% is £5,368.11 with a daily rate of £34.19 per day (note to candidates: you should assume these figures are correct).
John Evans will sign the statement of truth.
Thanks
Partner
Note to candidates: You should provide your answer on the template provided (it is already in the answer box). Please do not record your name on the answer template.
————————————————————
ATTACHMENT 1 – Draft statement of John Evans
I, John Evans of 4, Dawlish Road, London N3 4SS, will say as follows:
1. I am the managing director of Addison Builders Limited, a company based in North London. The company specialises in building and renovating luxury residential homes. I set up the company in 2018 with my two brothers and it is very much a family-run business.
2. On 2 September 2024, I was contacted by Maria Humphries, who had been given my name by a previous customer. Maria and her husband, Ian, had bought a very run-down property in North London (6 Highbury Way, N7 5RD), which had land around it. The couple wanted to transform this into a six-bedroom luxury house. They had already had the plans drawn up by the architect and had received planning permission for the build.
3. On 4 September 2024, I visited Maria and Ian at the premises and drew up a detailed costing of the work involved. The work was extensive as the existing property was badly in need of renovation and needed to be extended to a six-bedroom property. I calculated the total cost of the work to be £220,000 and estimated that the job would take approximately nine months.
4. On 6 September 2024, I met again with Maria and Ian and provided them with our standard form building services contract (note to candidates: this contract will be supplied by John Evans). This clearly set out the schedule of payments required and the detailed specification of the work. Maria and Ian were happy with the contract and signed it that day. It was agreed that work would commence on 26 September 2024 and the job would be completed by 4 July 2025.
5. Under the terms of our contract, the payments were staggered in four instalments, in accordance with the following:
• 20% (£44,000) of the cost was required within seven days of the contract, by 13 September 2024;
• 25% (£55,000) within three months of the contract, by 6 December 2024;
• 25% (£55,000) within six months of the contract, by 6 March 2025; and
• 30% (£66,000) on completion of the job.
6. Maria explained to me that they were currently in the process of selling their existing apartment in London, which would fund the majority of the work on the new house, although the initial payment would come from their savings. However, she assured me that the payment schedule would work for them as they had already found a buyer for their apartment and were due to exchange contracts in two weeks.
7. On 13 September 2024, I received the first payment from Maria and Ian, of £44,000.
8. We started the work on Maria and Ian's home on 26 September 2024. The next scheduled payment was due on 6 December 2024. However, on 2 December 2024 at a meeting at 6 Highbury Way, Maria and Ian told me they had still not sold their apartment and asked me if I would be prepared to wait a couple of months more for the money. I had developed a good working relationship with the couple by this stage and I could see the difficult predicament that they were in. Therefore I agreed when I spoke to them to allow them, without penalty, to pay the next instalment on 7 February 2025 when, hopefully, their property would have sold.
9. In February 2025 Maria and Ian had still not sold their apartment as their new prospective buyers were experiencing delays in the property chain. However, Maria had managed to borrow some money from her parents and was able to offer me £20,000 to keep the work going. At a meeting with Ian and Maria at 6 Highbury Way on 7 February 2025 I agreed to accept £20,000 on this basis. Maria was four months pregnant and was desperate to be in the new home when the baby was born. Maria paid me the £20,000 on 7 February 2025, bringing the total amount paid to date up to £64,000.
10. In May 2025, the project was going well and I was expecting to finish the job on 4 July 2025 as planned. Maria and Ian had exchanged contracts selling their apartment but there was a delayed completion date as the buyer was overseas. To make things worse, Maria then gave birth to the baby three months early and she and Ian spent most of their time at the hospital with their newborn. I felt very sorry for the couple and I therefore met with them at 6 Highbury Way on 20 May 2025 and agreed, orally, that they could pay me all the outstanding payments on completion of the job provided they did so on the day the job finished. I agreed that this would replace our original agreement as to the scheduled payments.
11. On 4 July 2025, I finished work on Maria and Ian's new home and they seemed to be happy with it, although it was a difficult time for them as their baby was still not well enough to come home. I handed them a final bill in the amount of £156,000 on 4 July 2025.
12. On 10 July 2025 I had still not heard anything from the couple and I telephoned them to see what the hold-up was. I understood that their apartment in London had sold and that there should be no further reason why they could not make the final payment. I spoke with Maria on the telephone very briefly but she cut me short and simply told me that she would get Ian to ring me.
13. The next day, I had still heard nothing and so I sent an urgent reminder email telling Ian that I now needed the account to be settled immediately. He did not respond to this email. I sent a more strongly-worded letter to them both on 15 July 2025 but they did not reply to this either. I heard from one of my contractors that there was some suggestion from Ian that the couple were not happy with the finish on the house, although I do not really understand this as they had not said anything like that to me.
14. On 29 July 2025 I realised that I had no choice but to contact solicitors on the matter. They have been dealing with this ever since.
I believe that the facts stated in this witness statement are true. I understand that proceedings for contempt of court may be brought against anyone who makes, or causes to be made, a false statement in a document verified by a statement of truth without an honest belief in its truth.
John Evans
Dated: [ ] December 2025
Not ready to write yet? See an example answer and its marking
Your answer
The timer starts when you begin typing45:00
125 words
This question and its performance indicators are SQE2 sample material and remain the property of the SRA. The SRA gives no warranty as to the accuracy of their reproduction or use here. Our marking, feedback and example answers are provided by Mistry AI and are not endorsed by the SRA or Kaplan. Source: SQE2 sample questions on the SQE website.